Day 1 – August 8, 2009

Clear crawlspace and paint foundation

Set floor joists

Lay floor decking

Sheath panels and run exterior walls

Run interior walls

Tie walls together, straighten and brace

Install lower porch package

 

Day 2 – August 15, 2009

Prep and run trusses

Install windows and trim packages

Install interior framing – wind bracing, deadwood, attic stairs

Deck roof

Install sub-fascia, barge rafters and drip edge

Felt roof

Set up for siding – trim, corner boards, skirt board, drip cap and starter strip

 

Day 3 – August 22, 2009

Shingle roof

Insulate walls and ceiling

Begin siding and caulking

Install underlayment in kitchen, dining room and bathroom

 

Day 4 – August 29, 2009

Finish insulation

Finish siding and caulking

Begin painting exterior – siding, foundation, window trim

Build side porch and ramp

 

Day 5 – September 12, 2009

Finish exterior painting

Begin interior painting

Install baseboard, window sills and miscellaneous interior trim

Install kitchen cabinets and countertops

Begin soffit and fascia

 

Day 6 – September 19, 2009

Touch up exterior painting

Finish soffit and fascia

Finish interior painting

Install porch railings

 

Day 7 – September 26, 2009

Install doorknobs and bathroom hardware

Clean house interior

Touch up interior painting

Complete miscellaneous items

Rake and clear lot

Landscape

DEDICATE NEW HOME!