Day 1 –
Clear crawlspace and
paint foundation
Set floor joists
Lay floor decking
Sheath panels and run
exterior walls
Run interior walls
Tie walls together,
straighten and brace
Install lower porch
package
Day 2 –
Prep and run trusses
Install windows and trim
packages
Install interior framing
– wind bracing, deadwood, attic stairs
Deck roof
Install sub-fascia, barge
rafters and drip edge
Felt roof
Set up for siding – trim,
corner boards, skirt board, drip cap and starter strip
Day 3 –
Shingle roof
Insulate walls and
ceiling
Begin siding and caulking
Install underlayment in
kitchen, dining room and bathroom
Day 4 –
Finish insulation
Finish siding and
caulking
Begin painting exterior –
siding, foundation, window trim
Build side porch and ramp
Day 5 –
Finish exterior painting
Begin interior painting
Install baseboard, window
sills and miscellaneous interior trim
Install kitchen cabinets
and countertops
Begin soffit and fascia
Day 6 –
Touch up exterior
painting
Finish soffit and fascia
Finish interior painting
Install porch railings
Day 7 – September 26, 2009
Install doorknobs and
bathroom hardware
Clean house interior
Touch up interior
painting
Complete miscellaneous
items
Rake and clear lot
Landscape
DEDICATE NEW HOME!